PJM Files Amended Backstop Proposal: What Changed and What Happens Next

Writer: Tony Zelinski
Tony Zelinski
39 minutes ago
2 min read
PJM Files Amended Backstop Proposal: What Changed and What Happens Next
PJM Files Amended Backstop Proposal: What Changed and What Happens Next

On Thursday, October 29, 2026, PJM filed its amended Section 205


Reliability Backstop Procurement proposal with FERC — the refile PJM had targeted since its September 29 order suspended the original procurement for five months.


What the amended filing does


The filing addresses the three issues FERC flagged in its September 29 order:


  • Cost allocation: Backstop costs will now be allocated based on Large Load growth — measured from actual summer peak load in 2026 to the forecast for the 2028/2029 delivery year. Electric distribution companies will provide firm Large Load growth figures, assigned by each zone's contribution. This is the cost-causation fix FERC and the Department of Energy both pressed for: costs follow the load growth driving the need, rather than spreading to existing ratepayers.


  • LSE credit requirements: Revised to a lower uniform credit rate with revised payment terms.


  • LSE exit responsibility: An exiting load-serving entity remains responsible for backstop charges for the remainder of the commitment term.


  • Municipal/cooperative opt-out removed: The prior provision allowing municipal and cooperative utilities to opt out is gone.


The filed timeline


  • Bid window: March 1–28, 2027


  • Final target/supply determined: April 28, 2027


  • Results posted: May 10, 2027


These dates supersede the draft timeline circulated in PJM's October 22 stakeholder materials.


The procurement itself


The roughly 6,800 MW shortfall for the 2028/29 delivery year will be recalculated with updated information, and the target will be reduced by any megawatts procured through executed bilateral contracts. Resources can still secure terms of up to 15 years, with a maximum willingness to pay of a MW-weighted average of $555/MW-day.


What is still open


FERC has not yet acted on the amended filing. Two questions remain unresolved: whether FERC will hold its paper hearing in abeyance while it considers the new proposal, and the February 28, 2027 suspended effective date from the original order. The auction remains suspended until FERC acts — this filing is a proposal, not an approval.


What this means for buyers


For commercial and industrial customers in PJM, the picture is now clearer but not yet final. The timeline is concrete for the first time since September, and the cost-allocation fix means large-load growth — principally data centers — bears the cost it drives, rather than existing load. Until FERC rules, however, 2028/29 capacity costs still carry an open backstop component. No procurement action is required today, but any 2028/29 contracting should account for the possibility of backstop-related costs landing in that delivery year. We will update this note when FERC responds.


This update is market information for planning purposes and is not legal or regulatory advice.




Winter is almost here...

Would you like a review of your facility's Winter Energy strategy? We are here to help!



 
 
 

Comments


Commenting on this post isn't available anymore. Contact the site owner for more info.
bottom of page